At this time (July 14,
2008) fundraising efforts have ceased on this project.
Although we raised almost $100,000 more than the original goal,
expenses from the time of the estimates in 2007 have risen
sharply.
However, the project
appears to be moving along quite well, and we are still planning on
having this project completed by Sept. 6, 2008, when we will have
our Plaza Celebration. All major design elements are still in
place: 15, benches, six landscape plaques bordering the two
walkways, and the pedestal design, including light at the foot of
the statue (atop the pedestal).
In the meantime, for
those of you who would like a little recent history of the project,
and the fundraising efforts that led us where we are today:
A
bit of background:
After several years
of planning and fundraising by a former organization, the Seattle
Statue of Liberty Plaza Project was formed in mid-2007 to
finish this project. Our efforts were jump-started by a $50,000
donation from the City of Seattle, announced by Mayor Greg
Nickels and City Councilman Tom Rasmussen on Sept. 11, 2007, and
supported unanimously by the City Council, when the newly-cast
statue was put temporarily on the old base.
The new goal, as
determined by the cost estimates of the plan for the plaza
developed over three years by a pro bono Design Team of architects
and Designers with input from the West Seattle Community, The
Seattle Parks Department, and concerned citizens, was $157,000.
At that time, a representative of the City estimated if the
citizens wished the project to be finished by July, 2008, the goal
would have to be met by January 15, 2008.
The
goal to be met included the $50,000 from the City of
Seattle in the 2008 budget, and $10,550 left from the prior
fundraising organization. By the
January 15, 2008 date, however, we received, including the above
amounts, $174,940 by January 15, 2008. For more
details, see the Finance
page.
Better
yet, by the time fundraising "officially" ended on March
31, 2008, we had raised almost $100,000 more than the
original goal. However, not only have construction costs
risen substantially, but there have been some modifications to the
design. Primarily, several people and organizations,
including the Design Commission of the City of Seattle, were very
concerned about the benches not having backs. The concrete
itself was also an issue, since concrete does not hold heat well
and sitting on a cold concrete bench is not relaxing over any
period of time.
Ultimately,
it was determined that switching to wooden backs, at this time,
would not be possible, even with the extra money that had been
raised. The costs for redesign, as well as a suitable wood
product, were deemed excessive be a committee composed of SSLPP,
the SSLPP Design Team, Seattle Parks and Recreation, and the
architects hired by Parks to finalize the plaza design.
It
was possible to include wood planking on just the seating portion
of the benches, however. This has more of the feeling of
wood, and is far more pleasant to sit upon. Since that did
not involve major design changes, that improvement will be made.
It
appears funds are adequate to make these changes. The funds
are under the control of Urban Sparks, our Fiscal Sponsor.
Since SSLPP was formed only to see the project completed that the
people of West Seattle and the surrounding areas worked on for so
long, the organization will disband when this project is fully
concluded. Any remaining funds will simply remain with Urban
Sparks, whose main purpose is to support organizations like ours
seeking to build and/or improve parks and open spaces in the
Seattle area.
We
will be updating the Finance Page shortly
with more information.
If you have questions of any kind about the statue project, please contact us.